Overview
Resources
Notes
Phase | Requirements | Notes |
---|
Phase 1 | - New site creation with the new UCSB using the public affairs distribution
- Apigee modules installation
- Transfer current site content
- Setup and transfer workflow and rules
- Migrate user accounts
- Home page design
| - Phase 1 will include the migration of the site "as-is" to Drupal 8.
- We estimate the project to take about 160 hours
- The Apigee team has limited resources that will be available to assist, provide guidance, and testing for the migration.
|
Phase 2 | - Automate the lookup to check for Apigee module updates
- Automate the application of Apigee module update
- Connect to campus SSO
- Implement Apigee Teams feature
- Site redesign to accommodate additional areas
| - In Phase 2 we want to implement improvements to the site, such as SSO integration, the teams feature, better integration with the campus identity system, and some Drupal update automatons.
- There is a need for a web presence for the campus DevOps initiative. The developer portal was created initially as a generic developer resource site (developer.ucsb.edu). With the API platform being the main purpose of the site initially, it's design centers around this function. We are hoping we can redesign it to better fit the vision of serving the developer community in a wider capacity.
|
Phase 3 | - Account cleanup automation
- Move all components to AWS (database, existing code)
- Develop account cleanup code
- As part of the AWS migration we can migrate the Heroku components for the chatbot
| |